Michelle Tuesday Music School : STATUS Doors are hung, walls painted, electricity and lights in place, HVAC tied in, and ceilings installed. Now we need door hardware, baseboards, crown molding, reception counter, a thorough cleaning, steam-cleaning for the carpets, a final inspection, and certificate of occupancy. We should be done by Friday! We could have probably held our Grand Opening this Saturday as originally planned, but it's too close for comfort. If anything causes the final inspection to fail, the contractor will have to fix it, and that would delay our occupancy until Monday. Meanwhile, I need computers, a portable wall, promotional products, fliers to send home with the schools, and advertisements, all before next Sunday, which means the one-week delay benefits me anyway. I would say I need my security system in place, too, but I'm about to fire ADT. So I'll be starting from scratch on the security system. Maybe not from scratch - I did have another quote. I'm taking recommendations on security companies. And we've been taking calls and scheduling new students, which makes me very, very happy. |